1. Review the functions of the Historical Foundation and provide recommended changes to the City Council | City Manager’s Office | Start FY 2022 Q1 | Complete FY 2022 Q1
2. Update the Nance Farm Master Plan | City Manager’s Office | Start FY 2022 Q1 | Complete FY 2022 Q4
3. Develop a Nance Farm Master Plan implementation timeline | City Manager’s Office | Start FY 2022 Q3 | Complete FY 2022 Q4
4. Develop an operating plan with personnel recommendations | City Manager’s Office | Start FY 2022 Q3 | Complete FY 2022 Q4