Capital Improvement Projects (CIP)

Projects Updated Quarterly

Project Name: Danieldale Road
Project Location/Limits: West city limits to Westmoreland Road
Project Type: Street Widening
Project Description: Widen roadway to 4 concrete lanes (2 lanes per direction separated by raised median). Includes drainage
improvements, permanent traffic signal at Bolton Boone intersection, trail, landscape and street lighting
Project Status: Design is 30% complete
Last Update: Oct. 2020
City Contact: Tony Irvin

Project Name: Cove Meadow / Lake Grove Erosion Mitigation
Project Location/Limits: 1312/1316 Lake Grove Lane and 907 Cove Meadow Circle
Project Type: Drainage
Project Description: Erosion control treatments at two sites. The Cove Meadow site also includes replacing 650 feet of deteriorated sewer line
Project Status: Design is 60% complete
Last Update: Oct. 2020
City Contact: Tony Irvin

Project Name: Bee Branch Erosion Mitigation
Project Location/Limits: 1201 Whispering Oaks Drive
Project Type: Drainage
Project Description: Mitigation treatment to control erosion within a city drainage easement and into a portion of Bee Branch creek
Project Status: TBD
Last Update: Oct. 2020
City Contact: Tony Irvin

Project Name: 2019 Alley Reconstruction
Project Location/Limits: Misty Glen Dr/Dennis Dr & Ray Andra Dr/Vince Lane
Project Type: Alley
Project Description: Remove and reconstruct alley pavement
Project Status: Design is 80% complete
Last Update: Oct. 2020
City Contact: Tony Irvin

Project Name: Chattey Road
Project Location/Limits: Belt Line Road to Pleasant Run Road
Project Type: Street Reconstruction
Project Description: Replace existing asphalt pavement with concrete pavement. Includes drainage improvements, traffic calming elements, water line replacement, sewer line replacement, sidewalks, landscape and street lighting
Project Status: Construction is 20% complete
Last Update: Oct. 2020
City Contact: Tony Irvin

Project Name: 2020 Renovation and Replacement Phase 1
Project Location/Limits: Thunderbrook Circle, Clubbrook Circle, Meriweather Place, Meadowbrook Drive, Windingbrook Drive, Pebblebrook Drive
Project Type: Utilities
Project Description: Replace existing water and sewer lines
Project Status: Construction is 60% complete
Last Update: Oct. 2020
City Contact: Tony Irvin

Project Name: 2021 Renovation and Replacement
Project Location/Limits: Greenbrook Drive, Shadybrook Drive, Briarbrook Drive
Project Type: Utilities and Street Reconstruction
Project Description: Replace water and sewer lines and reconstruct pavement
Project Status: Design is 90% complete
Last Update: Oct. 2020
City Contact: Tony Irvin

Project Name: 2019 Street Reconstruction
Project Location/Limits: Peggs Street, Marble Canyon Drive, Parkerville Road
Project Type: Street Reconstruction
Project Description: Reconstruct asphalt pavement
Project Status: Construction
Last Update: Oct. 2020
City Contact: Tony Irvin

Project Name: 2020 Street Reconstruction
Project Location/Limits: Old Hickory Trail, Keysville Avenue, Stinnett Place, Reedsport Place, Silver Creek Dr.
Project Type: Street Reconstruction
Project Description: Reconstruct asphalt pavement
Project Status: Design is 90% complete
Last Update: Oct. 2020
City Contact: Tony Irvin

Project Name: Westmoreland Road
Project Location/Limits: Parkerville Road to Belt Line Road
Project Type: Street Expansion
Project Description: Widen roadway to 4 concrete lanes (2 lanes per direction separated by raised median). Includes drainage improvements, water line replacement, traffic signal at Eagle and Parkerville intersections, sidewalks, trailhead, landscape and street lighting
Project Status: Right of Way Acquisition
Last Update: Oct. 2020
City Contact: Tony Irvin

Project Name: Fire Station No. 2
Project Location/Limits: 206 S. Parks Drive
Project Type: Facilities
Project Description: Construction a new fire station that will replace the existing Station #262 located at 105 First Street. The new building will also house Fire Administration who will relocate from City Hall
Project Status: Construction is 98% complete
Last Update: Oct. 2020
City Contact: Tony Irvin

Project Name: Pleasant Run Road
Project Location/Limits: Cockrell Hill Road to Westmoreland Road
Project Type: Street Expansion
Project Description: Widen roadway to 4 concrete lanes (2 lanes per direction separated by raised median). Includes drainage improvements, water line replacement, sewer line replacement, sidewalks, landscape and street lighting
Project Status: Right of Way Acquisition
Last Update: Oct. 2020
City Contact: Tony Irvin

Project Name: Hampton Road Corridor Planning Study
Project Location/Limits: Belt Line Road to Pleasant Run Road
Project Type: Planning Study
Project Description: Master planning for economic redevelopment best uses and repurpose Hampton Road to align with redevelopment goals
Project Status: Project Scope Development
Last Update: Oct. 2020
City Contact: Tony Irvin

Project Name: Wintergreen Road Intersection Re-alignment
Project Location/Limits: West city limit at Wintergreen/Main St/Duncanville Rd Intersection
Project Type: Intersection
Project Description: Realign the existing intersection to remove the existing offset intersection configuration. Includes a traffic signal and bridge across Stewart Branch
Project Status: Construction is 60% complete
Last Update: Oct. 2020
City Contact: Tony Irvin - Dallas County is responsible for managing construction