commercial projects

Comfort Suites Hotel
• Location: Wintergreen Rd. West of I-35
• Project Status: 
Construction 100% complete, contractor going vertical (6/18)
                             Construction 100% complete, contractor going vertical (7/18)
                             Construction 99% complete awaiting final (8/18)
                             Construction 99% complete awaiting final (9/18)
                             Project complete awaiting final (10/18)
                             Project complete awaiting final (11/18)
• Projected Completion Fall 2018

  
The Village UMC

• Location: Wintergreen Rd. West of I-35
• Project Status:  
Awaiting pending Pre-Construction Meeting (6/18)
                             Awaiting pending Pre-Construction Meeting (7/18)
                             Awaiting pending Pre-Construction Meeting (8/18)
                             Awaiting pending Pre-Construction Meeting Documents (9/18)
                             Awaiting pending Pre-Construction Meeting Documents (10/18)
                             Pre-construction meeting complete (11/18)
• Projected Completion Pending  
   
 
Best Western - GLO Hotel
• Location: I-35 Frontage Rd. between The Meadows Pkwy and Southpointe Dr.
• Project Status: Civil Infrastructure Complete (ongoing work on interior) (6/18)
                             Civil Infrastructure Complete Awaiting Final Inspection/walk-through (7/18)
                             Civil Infrastructure Complete Awaiting Final Inspection/walk-through (8/18)
                             Complete, awaiting As-builts for final release (9/18)
                             Complete, awaiting As-builts for final release (10/18) 
                             Complete, awaiting As-builts for final release (11/18) 
• Structure Status: 99% Complete (5/18)
                                 99% Complete (6/18)
                                 99% Complete (7/18)
                                 99% Complete (8/18)
                                 99% Complete (9/18) 
                                 Complete (9/18)  

• Projected Completion Summer 2018

Desoto House of Peace Community Center
• Location: Belt Line in front of Summit Parks
• Project Status: 
Construction 10% complete, dirt work (6/18)
                             Construction 15% complete, utility work started (7/18)
                             Construction 25% complete, utility work ongoing (8/18)
                             Construction 40% complete, utility work ongoing (9/18)
                             Construction 50% complete, utility work ongoing (10/18)
                             Construction 50% complete, paving work started (11/18)
• Structure Status: TBD
• Projected Completion Fall 2018
    
 
Grocery Store - Lot 1, Block A 
• Location: North-West corner of belt Line Rd. and Westmoreland Rd.
• Project Status: 
Awaiting Pre-Construction Meeting (6/18)
                             Awaiting Pre-Construction Meeting (7/18)
                             Awaiting Pre-Construction Meeting (8/18)
                             Awaiting Pre-Construction Meeting (9/18)
                             Awaiting Pre-Construction Meeting (10/18)
                             Awaiting Pre-Construction Meeting (11/18)
• Structure Status: TBD
• Projected Completion TBD

DeSoto Nursing and Rehabilitation Center 
• Location: South-West corner of Hampton Rd. and Centre Park Blvd.
• Project Status: 
Awaiting Pre-Construction Meeting (6/18)
                             Awaiting Pre-Construction Meeting (7/18)
                             Awaiting Pre-Construction Meeting (8/18)
                             Awaiting Pre-Construction Meeting (9/18)
                             Awaiting Pre-Construction Meeting (10/18)
                             Awaiting Pre-Construction Meeting (11/18)
• Structure Status: TBD
• Projected Completion TBD

Athlos - Desoto K-8 Charter School 
• Location: South-East corner of Cockrell Hill Rd. and Wintergreen Rd.
• Project Status: 
Design Review of Traffic plan (6/18)
                             Design Review of Traffic plan (7/18)
                             Design Review of Traffic plan (8/18)
                             Design Review of Traffic plan (9/18)
                             Design Review of Traffic plan (10/18)
                             Design Review of Traffic plan (11/18)
• Structure Status: TBD
• Projected Completion TBD
 
 
Access Storage
• Location: South-East corner of Hampton Rd. and Danieldale Rd.
• Project Status: 
Construction 10% complete, dirt work (6/18)
                             Construction 15% complete, utility work started (7/18)
                             Construction 50% complete, utility work started (8/18)
                             Construction 60% complete, utility work started (9/18)
                             Construction 60% complete, utility work started (10/18)
                             Construction 65% complete, utility work completed (11/18)
• Structure Status: TBD
• Projected Completion TBD

La Quinta Inn & Suites
• Location: I-35 Frontage Rd. and Centre Park Blvd.
• Project Status: 
Awaiting Pre-Construction Meeting (6/18)
                             Awaiting Pre-Construction Meeting (7/18)
                             Awaiting Pre-Construction Meeting (8/18)
                             Awaiting Pre-Construction Meeting Documents (9/18)
                             Awaiting Pre-Construction Meeting Documents (10/18)
                             Awaiting Pre-Construction Meeting Documents (11/18)
• Structure Status: TBD
• Projected Completion TBD

E.R. Carpenter LP EPS Plant
• Location: South-West corner of Talon Dr. and Peregrine Way
• Project Status: 
Accepted for construction (6/18)
                             Awaiting Pre-Construction Meeting (7/18)
                             Construction 10% complete, utility work started (8/18)
                             Utility work 90% Complete (9/18)
                             Working on Tilt-up walls 25% Complete (10/18)
                             Working on Tilt-up walls 75% Complete (11/18)
• Structure Status: TBD
• Projected Completion TBD

VCA Animal Clinic
• Location: 201 N. Lyndalyn Ave.
• Project Status: 
Design Review (6/18)
                             Design Review (7/18)
                             Design Review (8/18)
                             Awaiting Pre-Construction Meeting (9/18)
                             Cleared to start construction (10/18)
                             Utility work 50% complete (11/18)
• Structure Status: TBD
• Projected Completion TBD

Holiday Inn & Suites Hotel
• Location: I-35 Frontage Rd. between The Meadows Pkwy and Wintergreen Rd.
• Project Status: 
Design Review (7/18)
                             Design Review (8/18)
                             Design Review (9/18)
                             Design Review (10/18)
                             Plans accepted for construction, awaiting pre-construction meeting (11/18)
• Structure Status: TBD
• Projected Completion: TBD

Fuzzy's Taco Shop
• Location:
228 Pleasant Run Rd.
• Project Status: 
Design Review (7/18)
                             Design Review (8/18)
                             Design Review (9/18)
                             Awaiting Pre-construction Meeting (10/18)
                             Awaiting Pre-construction Meeting (11/18)
• Structure Status: TBD
• Projected Completion: TBD

Mark at DeSoto Apartment Complex
• Location:
South-east corner of Belt Line Rd. and Westmoreland Rd.
• Project Status: 
Design Review (9/18)
                             Design Review (10/18)
                             Design Review (11/18)
• Structure Status: TBD
• Projected Completion: TBD

Hampton Retail Center
• Location:
1713 N. Hampton Rd.
• Project Status: 
Design Review (9/18)
                             Design Review (10/18)
                             Design Review (11/18)
• Structure Status: TBD
• Projected Completion: TBD
 
DeSoto Transitional Care Center
• Location:
108 Barrows Pl.
• Project Status: 
Design Review (9/18)
                             Design Review (10/18)
                             Plans accepted for construction, dirt work ongoing and awaiting pre-construction meeting (11/18)
• Structure Status: TBD
• Projected Completion: TBD

Southfield Park 35 - Building No. 5
• Location:
South-east corner of Old Hickory and Danieldale Rd.
• Project Status: 
Design Review (10/18)
                             Design Review (11/18)
• Structure Status: TBD
• Projected Completion: TBD