Subdivisions

The Homestead at Daniel Farm - Phase 1A 
68 lots – Residential
Project Status: Utilities installed, 50% complete (10/18)
                           Utilities installed, 75% complete (11/18)
                           Utilities installed, 90% complete, awaiting pavement placement to start (12/18)
                           Utilities installed, 80% complete, awaiting pavement placement to start (1/19)
                           Utilities installed, 80% complete, awaiting pavement placement to start (2/19)
                           Street and Alley Paving started, 65% complete (3/19)
Developer: Wildwood Development Company I, L.P.

Engineer: Dietz Engineering
Contractor: Wildwood Development Company I, L.P.

Summit Parks Phase 2 
72 lots – Residential
Project Status: Utilities installed, 50% complete (10/18)
                          Utilities installed, Project 50% complete (11/18)
                          Utilities installed, Project 60% complete (12/18)
                          Utilities installed, Project 65% complete (1/19)
                          Utilities installed, Starting pavement subgrade prep, Project 75% complete (2/19)
                          Subgrade prep, complete, paving started project 85% complete (3/19)
Developer: Alluvium Development

Engineer: Bannister Engineering
Contractor: Alluvium Development
 
Hidden Lakes Phase 1 
40 lots – Residential
Project Status:  Design Review (10/18)
                           Design Review (11/18)
                           Design Review (12/18)
                           Design Review (1/19)
                           Design Review (2/19)
                           Design Review (3/19)
Developer: Alluvium Development

Engineer: Bannister Engineering
Contractor: TBD

Hidden Lakes Phase 2 
31 lots – Residential
Project Status:  Design Review (10/18)
                           Design Review Complete (11/18)
                           Design Review Complete, Preliminary plat process started (12/18)
                           Design Review Complete, Preliminary plat process started (1/19)
                           Design Review Complete, Preliminary plat process ongoing (2/19)
                           Design Review Complete, Preliminary plat process ongoing (3/19)
Developer: Alluvium Development

Engineer: Bannister Engineering
Contractor: TBD

Cole Crossing Estates 
66 lots – Residential
Project Status: Design Review (10/18)
                          Design Review Complete (11/18)
                          Design Review Complete, Preliminary plat process started (12/18)
                          Design Review Complete, Preliminary plat process started (1/19)
                          Pre-Construction Meeting held on 2/8/19 (2/19)
                          Construction started (3/19)
Developer: Harlan Properties

Engineer: Land Design
Contractor: TBD

Trees Farm Phase I 
101 lots – Residential
Project Status: Utilities started (10/18)
                          Utilities 15% complete (11/18)
                          Utilities 60% complete (12/18)
                          Utilities 65% complete (1/19)
                          Utilities 65% complete (2/19)
                          Dirt work complete, utility work started, storm sewer still to be installed, project 80% complete (3/19)
Developer: Bloomfield Homes, LLP

Engineer: Engineering Concepts & Design, LLP
Contractor: Precision Management and Construction

 
Ten Mile Creek Estates  
89 lots – Residential
Project Status: Design Review (10/18)
                          Design Review (11/18)
                          Design Review (12/18)
                          Design Review (1/19)
                          Design Review (2/19)
                          Design Review (3/19) 
Developer: Harlan Properties, Inc.
Engineer: LandDesign
Contractor: TBD
 
Parkerville Meadows Phase 3
 
112 lots – Residential
Project Status: Design Review (10/18)
                          Design Review (11/18)
                          Design Review (12/18)
                          Design Review (1/19)
                          Accepted for Construction, awaiting Pre-con. (2/19)
                          Accepted for Construction, awaiting Pre-con. (3/19)
Developer: Kapsen Development Group, LLC

Engineer: Atlas Associates, Inc.
Contractor: TBD

Hampton Meadows Phase 2-B 
44 lots – Residential
Project Status: Design Review (10/18)
                           Design Review (11/18)
                           Design Review (12/18)
                           Design Review (1/19)
                           Design Review (2/19)
                           Design Review (3/19)
Developer: LGI Homes, LLC

Engineer: Pape-Dawson
Contractor: TBD

Summit Parks Phase 3 
58 lots – Residential
Project Status: Design Review (12/18)
                           Design Review (1/19)
                           Design Review (2/19)
                           Design Review (3/19)
Developer: Alluvium Development

Engineer: Bannister Engineering
Contractor: Alluvium Development