Subdivisions

Kentsdale Farm Phase III
67 lots – Residential
Project Status: Design Review (9/16)
                           Design Review (10/16)
                           Design Review (11/16)
                           Design Review (12/16)

                           Design Review (1/17)
                           Accepted for Construction - Awaiting Pre-Con (2/17)
                           Accepted for Construction - Pre-Con scheduled for April 4, 2017 (3/17)
                           Construction 10% Complete: Sanitary Sewer and Storm Drainage being Installed (4/17)
                           Construction 50% Complete: All Utilities Installed, paving remaining (5/17)
                           Construction 50% Complete: All Utilities Installed, paving remaining (6/17) 
Developer: Bloomfield Homes
Engineer: Engineering Concepts & Design, L.P.
Contractor: Conatser Construction 
  
Silver Creek Meadows Phase II
80 lots – Residential
Project Status: Construction 40% Complete: Water, Sanitary Sewer and Storm Drainage Installed (10/16)
                           Construction 60% Complete (11/16)
                           Construction 75% Complete (12/16)

                           Construction 75% Complete (1/17)
                           Construction 80% Complete, Awaiting Water Line Relocation (2/17)
                           Construction 95% Complete, Awaiting Water Line Relocation* (3/17)
                           Construction 99% Complete, Awaiting Water Line Relocation* (4/17)
                           Construction 99% Complete, Box Culvert and Paving remaining, Water Line Relocated on May 22, 2017 (5/17)
                           Construction 99% Complete, Paving over culvert box and connecting to streets remaining (6/17)
Developer: Skorburg Company

Engineer: Bannister Engineering
Contractor: Lacy Construction
   
Elerson Trace Park Tract 2
30 lots – Residential
Project Status: Design Review (9/16)
                           Design Review (10/16)
                           Design Review (11/16)
                           Design Review (12/16)

                           Design Review (1/17)
                           Design Review (2/17)
                           Design Review (3/17)
                           Design Review (4/17)   
                           Design Review (5/17)
                           Design Review (6/17)  
Developer: Wildwood Development Company I, L.P. 

Engineer: Crannell, Crannel & Martin
Contractor: TBD

The Homestead at Daniel Farm - Phase 1A 
68 lots – Residential
Project Status: Design Review (6/17)
Developer: Wildwood Development

Engineer: Dietz Engineering
Contractor: TBD