Future Projects

Chattey Rd. - Pleasant Run Rd. to Belt Line Rd. Improvements
Engineer: EJES, Inc.
Contractor: TBD
Project: Chattey Road is an existing two-lane asphalt roadway located within a residential community. The improved roadway will be a 27’ undivided concrete roadway with curb and gutter, closed drainage, sidewalks, retaining walls, sewer line crossings, water line replacement, landscaping and lighting.
Project Status: Design Phase at 95% completion. (9/16)
                             Appraisals are being completed for Right-of-Way Acquisition (10/16)
                             Appraisals are 20% Complete (11/16)
 • Construction anticipated to begin in early 2017

Joint MCIP Project - Dallas County
Engineer: TBD
Contractor: TBD
• Project:  Pleasant Run Rd. (Westmoreland Rd. – Cockrell Hill Rd.), 2 lane concrete roadway w/curb and gutter and storm drain. 
Project Status: Pre-Design - Consultant to be selected fall 2016 (9/16)
                             Preparing RFQ for consultant selection (10/16)
                             RFQ advertised (11/16)
 Construction anticipated to begin in 2018 
 
Fire Station #2 Relocation
Architect: Architect Design Group, Inc. (ADG) 
Contractor: TBD
Project: A new Fire Station With Fire Administration offices will be constructed in the vicinity of Parks Dr. and Belt Line Rd. Upon  completion of the new Fire Station, the existing Fire Station at Hampton Rd. and First St., will be removed.
Project Status: Design Phase 85% complete (9/16)
                             Design Phase 90% complete (10/16)
                             Design Phase 90% complete (11/16)
Construction anticipated to begin 2017

Corner Theatre
Architect: PBK Architects, Inc. 
Contractor: TBD
Project: The corner Theater of Town Center will be reconstructed into a "Black Box," theatre concept. This renovation will allow a variety of users to lease this area for different events including: Theatre events, receptions, dinners, etc.
Project Status: Design Phase 90% complete (9/16)
                             Design Phase 100% complete Bidding slated to begin in 
December 2016 (11/16)
Construction anticipated to begin Spring 2017