Future Projects

Chattey Rd. - Pleasant Run Rd. to Belt Line Rd. Improvements

Engineer: EJES, Inc.
Contractor: TBD
Project: Chattey Road is an existing two-lane asphalt roadway located within a residential community. The improved roadway will be a 27’ undivided concrete roadway with curb and gutter, closed drainage, sidewalks, retaining walls, sewer line crossings, water line replacement, landscaping and lighting.
Project Status: Design Phase at 95% completion. (9/16)
Construction anticipated to begin in early 2017

Joint MCIP Project - Dallas County

Engineer: TBD
Contractor: TBD
• Project:  Pleasant Run Rd. (Westmoreland Rd. – Cockrell Hill Rd.), 2 lane concrete roadway w/curb and gutter and storm drain. 
Project Status: Pre-Design - Consultant to be selected fall 2016 (9/16)
Construction anticipated to begin in 2017

Fire Station #2 Relocation
Architect: Architect Design Group, Inc. (ADG) 
Contractor: TBD
Project: A new Fire Station With Fire Administration offices will be constructed in the vicinity of Parks Dr. and Belt Line Rd. Upon 
                 completion of the new Fire Station, the existing Fire Station at Hampton Rd. and First St., will be removed.
Project Status: Design Phase 85% complete (9/16)
Construction anticipated to begin in 2017

Corner Theatre
Architect: PBK Architects, Inc. 
Contractor: TBD
Project: The corner Theater of Town Center will be reconstructed into a "Black Box," theatre concept. This renovation will allow a variety
                 of users to lease this area for different events including: Theatre events, receptions, dinners, etc.
 • Project Status: Design Phase 90% complete (9/16)
Construction anticipated to begin in early 2017