Current Projects

 2014 Water/Wastewater Renovation & Replacement Project
(Belt Line Rd. – east of Hampton to Chattey Rd.)
• Engineer: Dick Perkins, P.E.
Contractor: Reytech Services
Project: The 2014 R & R Project includes the replacement of an existing 4“ water main located on both sides of Belt Line Rd. east of Hampton Rd. to Chattey Rd., Polyvinyl Chloride (PVC) pipe. 

Project Status: 
Construction is 25% complete (5/17)
                             Construction is 75% complete (6/17)
                             Construction is 85% complete (7/17)
                             Construction is 90% complete (8/17)
                             Construction is 95% complete (9/17)
                             Construction is substantially complete (10/17)
                             Construction is substantially complete (11/17)
Projected Completion Fall 2017 
 
2016 Water/Wastewater Renovation & Replacement Project - Phase 1
 
Deborah Avenue, David Avenue, Basin “B” Outfall Lines
• Engineer: Dick Perkins, P.E.
Contractor: No Dig Tech.
Project: The 2016 R & R Project includes various locations with varying degrees of deterioration of the existing clay tile sewer lines and cast iron water lines. In most cases the infrastructure is 40-50 years old. The water and sewer main lines will be replaced with
Polyvinyl Chloride (PVC) pipe. In addition, water service lines will be replaced (City side of the meters) and sewer lines will be replaced up to the property lines with cleanouts being installed at the property line. 

Project Status: 
Easement Acquisition is 33% Complete, Project Bid on May 25, 2017 (5/17)
                             Easement Acquisition is 66% Complete (6/17)
                             Easement Acquisition Completed (7/17)
                             Project has been split into two phases. Phase I will be completed with the TIPS Buy Board (8/17)
                             and presented to City Council for award during September. Phase II will bid in October 2017
                             Phase 1 contract awarded on August 19, 2017 (9/17)
                             Construction started (10/17)
                             Construction is 35% complete (11/17)
Projected Completion Summer 2018

2016 Water/Wastewater Renovation & Replacement Project - Phase 2
N. Westmoreland Rd. Water Line (St. Anne Episcopal Church North to Cedar Rapids Ln. )
• Engineer: Dick Perkins, P.E.
Contractor: TBD
Project: The 2016 R & R Project includes various locations with varying degrees of deterioration of the existing clay tile sewer lines and cast iron water lines. In most cases the infrastructure is 40-50 years old. The water and sewer main lines will be replaced with
Polyvinyl Chloride (PVC) pipe. In addition, water service lines will be replaced (City side of the meters) and sewer lines will be replaced up to the property lines with cleanouts being installed at the property line. 
Project Status: 
Easement Acquisition is 33% Complete, Project Bid on May 25, 2017 (5/17)
                             Easement Acquisition is 66% Complete (6/17)
                             Easement Acquisition Completed (7/17)
                             Project has been split into two phases. Phase I will be completed with the TIPS Buy Board (8/17)
                             and presented to City Council for award during September. Phase II will bid in October 2017
                             Phase II contract will be advertised for bids starting on October 8, 2017 (9/17)
                             Phase II has been bid (10/17)
                             Phase II has bid and will be presented to City Council for award on December 19 2017 (11/17)
Projected Completion Summer 2018

2017 Street Reconstruction
Winston Dr. (Old Hickory - Danieldale), Silver Creek Dr. (Peggs - 220' West), Hampton Rd. (Warbler - S. City Limits), Timberline Court - Alternate, Forest Glen (Sapling - Sumac) - Alternate, Peggs (Silver Creek - Pleasant Run) - Alternate, Faye St. (Young - Tara) - Alternate
• Engineer: Dick Perkins, P.E.
Contractor: Reynolds Asphalt
Project: The 2017 Street Reconstruction is included annual reconstruction of residential and collector asphalt streets. The scope of work for this project will consist of pulverization of the existing asphalt, cement stabilization of the base material to a depth of 6", and construction of a new 6" asphalt roadway. In addition, Hampton Rd., (Warbler to S. City Limits) will receive a 2 inch mill overlay (M&O) treatment to further extend the life of the pavement.
Project Status: Design 85% Complete (10/17)
                             Construction is 95% complete (11/17)
Projected Completion Summer

Miscellaneous Valve Replacement
Polk St. (at The Meadows Pkwy), Polk St. (Belt Line and Polk St.), Belt Line Rd. (Parks Elevated Water Tower)
• Engineer: Dick Perkins, P.E.
Contractor: Canary Construction
Project: The scope of this project is to remove replace existing broken valves on a 24" (inch) waterline on Polk St. (at two locations) and on Belt Line Rd. These valves are a necessity in order to isolate sections of the water main in the event of a required repair. The scope of this project includes pavement and sidewalk removal and replacement.
Project Status: Design Complete (10/17)
                             Construction to begin December 4, 2017 (11/17)
Projected Completion Summer 2018