Current Projects

 2014 Water/Wastewater Renovation & Replacement Project
(Belt Line Rd. – east of Hampton to Chattey Rd.)
• Engineer: Dick Perkins, P.E.
Contractor: Reytech Services
Project: The 2014 R & R Project includes the replacement of an existing 4“ water main located on both sides of Belt Line Rd. east of Hampton Rd. to Chattey Rd., Polyvinyl Chloride (PVC) pipe. 

Project Status: Design Complete (9/16) 
                             Easement Acquisition 90% Complete (10/16)
                             Easement Acquisition 100% Complete (11/16)
                             Project advertised and bids were opened (12/16)

                             Construction contract schedule to be presented to City Council, 2nd meeting in February (1/17)
                             Construction contract delayed to 1st meeting in March (2/17)
                             Construction contract approved by City Council, construction to begin in April 2017 (3/17)
                             Construction started on the south side of Belt Line Rd., behind Ace Hardware Center (4/17)
                             Construction is 25% complete (5/17)
                             Construction is 75% complete (6/17)
                             Construction is 85% complete (7/17)
                             Construction is 90% complete (8/17)
                             Construction is 95% complete (9/17)
Projected Completion Summer 2017 
 
2016 Water/Wastewater Renovation & Replacement Project - Phase 1
 
Deborah Avenue, David Avenue, Basin “B” Outfall Lines
• Engineer: Dick Perkins, P.E.
Contractor: No Dig Tech.
Project: The 2016 R & R Project includes various locations with varying degrees of deterioration of the existing clay tile sewer lines and cast iron water lines. In most cases the infrastructure is 40-50 years old. The water and sewer main lines will be replaced with
Polyvinyl Chloride (PVC) pipe. In addition, water service lines will be replaced (City side of the meters) and sewer lines will be replaced up to the property lines with cleanouts being installed at the property line. 

Project Status: Design Complete (10/16)
                             Easement Acquisition pending (11/16)
                             Easement Acquisition pending (12/16)

                             Easement Acquisition pending (1/17)
                             Easement Acquisition pending (2/17)
                             Easement Acquisition pending (3/17)
                             Easement Acquisition pending (4/17)
                             Easement Acquisition is 33% Complete, Project Bid on May 25, 2017 (5/17)
                             Easement Acquisition is 66% Complete (6/17)
                             Easement Acquisition Completed (7/17)
                             Project has been split into two phases. Phase I will be completed with the TIPS Buy Board (8/17)
                             and presented to City Council for award during September. Phase II will bid in October 2017
                             Phase 1 contract awarded on August 19, 2017 (9/17)
Projected Completion Summer 2018

2016 Water/Wastewater Renovation & Replacement Project - Phase 2
N. Westmoreland Rd. Water Line (St. Anne Episcopal Church North to Cedar Rapids Ln. )
• Engineer: Dick Perkins, P.E.
Contractor: TBD
Project: The 2016 R & R Project includes various locations with varying degrees of deterioration of the existing clay tile sewer lines and cast iron water lines. In most cases the infrastructure is 40-50 years old. The water and sewer main lines will be replaced with
Polyvinyl Chloride (PVC) pipe. In addition, water service lines will be replaced (City side of the meters) and sewer lines will be replaced up to the property lines with cleanouts being installed at the property line. 
Project Status: Design Complete (10/16)
                             Easement Acquisition pending (11/16)
                             Easement Acquisition pending (12/16)

                             Easement Acquisition pending (1/17)
                             Easement Acquisition pending (2/17)
                             Easement Acquisition pending (3/17)
                             Easement Acquisition pending (4/17)
                             Easement Acquisition is 33% Complete, Project Bid on May 25, 2017 (5/17)
                             Easement Acquisition is 66% Complete (6/17)
                             Easement Acquisition Completed (7/17)
                             Project has been split into two phases. Phase I will be completed with the TIPS Buy Board (8/17)
                             and presented to City Council for award during September. Phase II will bid in October 2017
                             Phase II contract will be advertised for bids starting on October 8, 2017 (9/17)
Projected Completion Summer 2018